County Rd #10 repairs on schedule

Great News from the United Counties of Leeds and Grenville today.  The project is progressing well and should be on track for a completion in accordance with the schedule.

The Contractor plans to place 5 precast units for Stage 1 at the Hagan culvert on Friday October 23. Backfilling will commence immediately and traffic switch-over should take place this coming weekend.  The “tremie” footing for Crosby Creek will be cast on Friday and the reinforced concrete footings will be cast on Monday October 26. The precast sections for Crosby will be installed by crane on Tuesday or Wednesday next week, followed immediately by the wing wall segments.

Looking forward to the Friday, November 6!