Update on Village new waste water system

The contract between the Village and the builder of the new waste water system requires the contractor to pay for the cost of hauling effluent this winter and spring.  The new system was to have been fully operational by November 21, 2017.  By that date, the Village had lowered the lagoon levels significantly.  Because the system was not operational on time, it became necessary to haul effluent to another municipality for several days in late January.  The cost of hauling was covered by the contractor.

The spring thaw and last weekend’s heavy rains resulted in excessive flows to the lagoons, decreasing the available capacity in the sewage lagoons. Hauling began on Thursday.  Again the cost of hauling is covered by the liquidated damages section of our contact and is being paid by the contractor.

We are confident that if the new system had been operational on November 21, no hauling would have been required this year.  We are also confident that moving forward, the new system is more than adequate to handle our sewage.

I will advise when the hauling is terminated.

Please call if you have any questions.  9195

 

 

 

Sand Beach rated #1 Best Beach

Today, the Wedge, a new on-line “voice in Eastern Ontario” rates Sand Beach as #1 of the 3 best beaches in Eastern Ontario.  Last week HGTV ranked Westport # 4 of the “20 of the Best off the Radar Spots for a Vacation Home in Canada”.  Take another moment and view the link and then swagger – a little more than last week!

https://thewedge.live/2018/04/18/best-beaches-three-summer-destinations/

Village of Westport successful in obtaining Ontario Trillium Fund Grant.

The Ontario Trillium Fund has awarded the Village a $56,500 grant to build an accessible, covered stage in Lockwood Memorial Field and Park.  The grant covers all costs including the installation of electrical and landscaping.  Village Council & Staff and the Parks and Recreation Advisory Committee are pleased that Westport was successful in this very competitive process and have thanked the Ontario Trillium Fund for its support.
 

The improvements to Lockwood Memorial Field and Park over the past three years have only been possible through fund raising and grants.  The 2015 grant from Lockwood Foundation has been a significant boon and enabled the Village to implement its plan for the park.  No tax dollars have been spent on the improvements.

The stage will be used to bring groups and people together for arts, cultural and heritage festivals and family events.  Community groups and members will now have a venue to bring people together – regardless of the weather.

The project has been awarded to Scott Blair Construction and it is our expectation that it will be operational this summer.

How exciting!!!!!!